Developments at San Martinho Beach Club

Construction is continuing rapidly on Villa’s 31, 32 and 33 in our Villa Praia, now boasting a growing number of privately owned villas along the powder soft, white sand beach of the lagoon.

Internal Progress

  • Plumbing and electrical – complete
  • Tiling – 85% – complete
  • Painting, primer and first coat to ceilings and walls – complete
  • Kitchen and bedroom cupboards – on going

External Progress

  • Pool installed, pool pump and filter installation – on going
  • Patio tiling – 35% complete
  • Installation of fascia’s – complete
  • Painting, primer coat complete and first coat paint – on going
  • Backfilling and compacting around unit and prepping for paving – on going
  • External sanitation systems and water connection – complete