Construction is continuing rapidly on Villa’s 31, 32 and 33 in our Villa Praia, now boasting a growing number of privately owned villas along the powder soft, white sand beach of the lagoon.
Internal Progress
- Plumbing and electrical – complete
- Tiling – 85% – complete
- Painting, primer and first coat to ceilings and walls – complete
- Kitchen and bedroom cupboards – on going
External Progress
- Pool installed, pool pump and filter installation – on going
- Patio tiling – 35% complete
- Installation of fascia’s – complete
- Painting, primer coat complete and first coat paint – on going
- Backfilling and compacting around unit and prepping for paving – on going
- External sanitation systems and water connection – complete